Agree with Zoltan, if it’s a WBS Summary you have added it does not need to be linked, but it does not seem that it is what you have added.
Is the summary you have added a Finish Milestone or Level of Effort as a summary.
If it is a Finish Milestone, make sure that this is the successor to the last activity.
If it is a Level of Effort used as a summary, then the start should be linked with the start of the first activity & the end linked with the last activity Finish to Finish.
Steven
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Wed, 2018-06-06 14:49
you dont have to link it it automatically summarizes the wbs that it is assoicated with it will span from the earliest start date of an actviity in that wbs to the latest finish date of the last activity in that wbs group. It is correct
Member for
8 years 1 monthAgree with Zoltan, if it’s a
Agree with Zoltan, if it’s a WBS Summary you have added it does not need to be linked, but it does not seem that it is what you have added.
Is the summary you have added a Finish Milestone or Level of Effort as a summary.
If it is a Finish Milestone, make sure that this is the successor to the last activity.
If it is a Level of Effort used as a summary, then the start should be linked with the start of the first activity & the end linked with the last activity Finish to Finish.
Steven
Member for
16 years 3 monthsyou dont have to link it it
you dont have to link it it automatically summarizes the wbs that it is assoicated with it will span from the earliest start date of an actviity in that wbs to the latest finish date of the last activity in that wbs group. It is correct