There is no need to repeat the process for different calendars. DaysPerMonth in MSP is a singular property of a Project, not of a Calendar, and it only occurs once in a project xml file. (P6's XML importer multiplies the Project|HoursPerDay by the Project|DaysPerMonth to arrive at an HoursPerMonth that it then writes to each non-elapsed-duration calendar in P6.)
Member for
19 years 1 month
Member for19 years1 month
Submitted by Thomas Nicholson on Wed, 2018-05-30 15:13
The issue is caused by the incorrect calendar setting inside Microsoft Project.
The total working hours per year in P6 is
366 Days *24 hours / day = 8784 hours / year
The Microsoft Project XML file defined more then 31 working days per week. This violation of the business rules hence P6 import function stopped and report the above error.
31 days X 12 months x 24 hours = 8928 hours /year
This problem can be fixed either in Microsoft Project (MSP) or in MSP XML file
A. Microsoft Project method
1. Open the problem project in Microsoft Project
2. Select Tools -> "Change Working Time" from the pull down menu to open the "Change Working Time" window
3. Select a calendar from the "For Calendar" drop down section.
4. Single Click Options icon at the bottom in the "Change Working Time" window.
5. Click the "Calendar" tab in the top of Options window
6. Modify the days per month to 30.5 then click OK
Repeat 3 to 7 to check all calendars setting.
7. Export the project to XML format then import it to P6.
B. Without MSP installed
1. Open the XML file in a text editor.
2. Search for "<DaysPerMonth>" XML attribute.
3. Change the value in between the <DaysPerMonth> and </DaysPerMonth> to 30.5
ie <DaysPerMonth>30.5</DaysPerMonth>
4. Repeat step 2 and 3 until all values had modified
Member for
16 years 3 monthsthanks both Toms
thanks both Toms
Member for
18 years 11 monthsPerfect diagnosis from
Perfect diagnosis from Zoltan. One clarification:
There is no need to repeat the process for different calendars. DaysPerMonth in MSP is a singular property of a Project, not of a Calendar, and it only occurs once in a project xml file. (P6's XML importer multiplies the Project|HoursPerDay by the Project|DaysPerMonth to arrive at an HoursPerMonth that it then writes to each non-elapsed-duration calendar in P6.)
Member for
19 years 1 monthZoltan, as usual you're a
Zoltan, as usual you're a star. Thank you for that, I shall get started immediately.
Kind regards,
Thom
Member for
16 years 3 monthsThe issue is caused by the
The issue is caused by the incorrect calendar setting inside Microsoft Project.
The total working hours per year in P6 is
366 Days *24 hours / day = 8784 hours / year
The Microsoft Project XML file defined more then 31 working days per week. This violation of the business rules hence P6 import function stopped and report the above error.
31 days X 12 months x 24 hours = 8928 hours /year
This problem can be fixed either in Microsoft Project (MSP) or in MSP XML file
A. Microsoft Project method
B. Without MSP installed