Baseline versus Actual Schedule Duration Complete Comparison

Member for

16 years 3 months

try using activity % complete and rolliing up the WBS

Member for

7 years 6 months

Thank you Zolfan; but what I am trying to figure out is something else. I will try to explain with an example. I have a schedule with 5 activities eact having "original duration" equal to 20. Total sum of activity durations is 5x20=100days. 

Lets say 20 days later only one activity should finish. It means that my activity duration progress is 20/100=20%. But in actual situtation, only one acticity is progressed by %50, which means 10days. My actual activity duration progress is 10%. 

How can I show these 10% and 20%s at WBS Summary level?

Thanks,

Gulsah 

Member for

16 years 3 months

why not use the existing field BL Project Duration and roll it up by wbs