Thank you Zolfan; but what I am trying to figure out is something else. I will try to explain with an example. I have a schedule with 5 activities eact having "original duration" equal to 20. Total sum of activity durations is 5x20=100days.
Lets say 20 days later only one activity should finish. It means that my activity duration progress is 20/100=20%. But in actual situtation, only one acticity is progressed by %50, which means 10days. My actual activity duration progress is 10%.
How can I show these 10% and 20%s at WBS Summary level?
Thanks,
Gulsah
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Fri, 2018-04-20 14:46
Member for
16 years 3 monthstry using activity % complete
try using activity % complete and rolliing up the WBS
Member for
7 years 6 monthsThank you Zolfan; but what I
Thank you Zolfan; but what I am trying to figure out is something else. I will try to explain with an example. I have a schedule with 5 activities eact having "original duration" equal to 20. Total sum of activity durations is 5x20=100days.
Lets say 20 days later only one activity should finish. It means that my activity duration progress is 20/100=20%. But in actual situtation, only one acticity is progressed by %50, which means 10days. My actual activity duration progress is 10%.
How can I show these 10% and 20%s at WBS Summary level?
Thanks,
Gulsah
Member for
16 years 3 monthswhy not use the existing
why not use the existing field BL Project Duration and roll it up by wbs