the order of the bars makes a difference also try moving the baseline bar either to top with the arrow up on the right hand side in the bars view or move it to the bottom of the order.
Member for
15 years 9 months
Member for15 years9 months
Submitted by Johannes Vandenberg on Fri, 2018-03-23 15:28
I have tried to change all settings, but it seems that by default it set like this.
Current bar and some other have setting that is OK (left = Start, right = Finish), BUT Baseline, Actual, Remaining bars does not have any settings and still I receive situation like the one that I am sending in the attached picture.
Orange bars are baseline and I don't need dates of them, blue bars are actual/remaining and I need to have Start date on it's left side such is Finish date on it's right side!
Now Start date is positioned on left side of Baseline Bar!
[[wysiwyg_imageupload:5492:]]
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Thu, 2018-03-22 13:00
Member for
16 years 3 monthsthe order of the bars makes a
the order of the bars makes a difference also try moving the baseline bar either to top with the arrow up on the right hand side in the bars view or move it to the bottom of the order.
Member for
15 years 9 monthsHi DejanHere a short video
Hi Dejan
Here a short video how to display the dates on the Gantt chart for the combined remaining work bar and the project baseline bar.
Regards Johannes
Member for
7 years 7 monthsI have tried to change all
I have tried to change all settings, but it seems that by default it set like this.
Current bar and some other have setting that is OK (left = Start, right = Finish), BUT Baseline, Actual, Remaining bars does not have any settings and still I receive situation like the one that I am sending in the attached picture.
Orange bars are baseline and I don't need dates of them, blue bars are actual/remaining and I need to have Start date on it's left side such is Finish date on it's right side!
Now Start date is positioned on left side of Baseline Bar!
[[wysiwyg_imageupload:5492:]]
Member for
16 years 3 monthsin the gantt area right click
in the gantt area right click bars
go to each bar and look at the bars label tab either delete it or modify it to your liking
also look at the current bar label and make sure what is listed is what you want displayed.