It seems that "activity steps" export to excel feature was available in prior version. Not sure, if this feature was removed or its just that I cannot find it.
I am not sure if I follow your recomendation correctly but I will give it a shot. Its worth trying.
Thanks
Sam
Member for
22 years 9 months
Member for22 years9 months
Submitted by Alexandre Faul… on Thu, 2018-02-08 11:44
I do not find a way to answer your first question; exporting the 4 fields relating to steps only exports the number of steps in each category;
to identify activities having a relationshio with an activity being in a different WBS node, you could use a Global Change to concatenate the Successor / Predecessor ID with the WBS in a user defined text field, and insert this UDF in the activities table
Member for
19 years 4 monthsAlexandre,Thanks for your
Alexandre,
Thanks for your comment.
It seems that "activity steps" export to excel feature was available in prior version. Not sure, if this feature was removed or its just that I cannot find it.
I am not sure if I follow your recomendation correctly but I will give it a shot. Its worth trying.
Thanks
Sam
Member for
22 years 9 monthsHello Sam,I do not find a way
Hello Sam,
I do not find a way to answer your first question; exporting the 4 fields relating to steps only exports the number of steps in each category;
to identify activities having a relationshio with an activity being in a different WBS node, you could use a Global Change to concatenate the Successor / Predecessor ID with the WBS in a user defined text field, and insert this UDF in the activities table
Alexandre