That did work. But this activity would be shown in the schedule and the Progress wont be calculated automatically which we would have to update by overself.
But as we require this is for the Support Staff or Support ITem or Equipment.
Ya the resource can be allocated at once like that but it wont show in a uniform maner as the same resource would be allocated to the paralell activities and as I have shown in the table "Porject Manager is 1, but if we allocate it to paralell activities then it will show as more than 1 Project Manager.
Hi Jatin.
I think you should select all activities once. And then in "assign" option click on resource. Then select all the common resource you want to add. And assign them.
Member for
14 years 7 monthsThanks Kannan,That did work.
Thanks Kannan,
That did work. But this activity would be shown in the schedule and the Progress wont be calculated automatically which we would have to update by overself.
But as we require this is for the Support Staff or Support ITem or Equipment.
Regards
Jithin
Member for
17 years 4 monthsHi Jithin,Add an activity as
Hi Jithin,
Add an activity as Level of Effort, from Project Start to Project Finish. Assign the common resources to this activity.
Regards
Kannan
Member for
14 years 7 monthsHi Adeb,Ya the resource can
Hi Adeb,
Ya the resource can be allocated at once like that but it wont show in a uniform maner as the same resource would be allocated to the paralell activities and as I have shown in the table "Porject Manager is 1, but if we allocate it to paralell activities then it will show as more than 1 Project Manager.
Regards
Jithin
Member for
9 years 3 monthsHi Jatin. I think you should
Hi Jatin.
I think you should select all activities once. And then in "assign" option click on resource. Then select all the common resource you want to add. And assign them.
Hope it is helpful.