Exporting External Activity Relationships to Excel

Member for

13 years 4 months

Hi Zoltan,

 

A flashback from 2005, I am trying to link external dependencies by adding them to the Master schedule export xls. Using P6 V23 I have followed your advice from 2005 (as above) but am not receiving the External Dependencies. I am also not receiving the External Early Start or Late Finish dates.

 

I have both projects open when exporting but only selecting the successor project. Your insight would be greatly appreciated.

Rod

Member for

13 years 4 months

Hi Zoltan,

 

A flashback from 2005, I am trying to link external dependencies by adding them to the Master schedule export xls. Using P6 V23 I have followed your advice from 2005 (as above) but am not receiving the External Dependencies. I am also not receiving the External Early Start or Late Finish dates.

 

I have both projects open when exporting but only selecting the successor project. Your insight would be greatly appreciated.

Rod

Member for

13 years 4 months

Hi Zoltan,

 

A flashback from 2005, I am trying to link external dependencies by adding them to the Master schedule export xls. Using P6 V23 I have followed your advice from 2005 (as above) but am not receiving the External Dependencies. I am also not receiving the External Early Start or Late Finish dates.

 

I have both projects open when exporting but only selecting the successor project. Your insight would be greatly appreciated.

Rod

Member for

16 years 3 months

make sure under the scheduling option that ignore external relationships is NOT checked

when you export make sure that you choose relationship and modify the export to include

Predecessor project 

successor project

predecessor wbs

successor wbs

also make sure that you have the rights to export the information for ALL of the projects that you have open