Yes, you are correct. The selected items are activity-related and will be automatically deleted if they are not found in the new record import and it works on me.
Another option you can choose is to use the 'Replace Existing Project' import action instead of selecting 'Update existing Project'. This will provide an exact copy of the imported Project.
Please Note: this import action will delete the whole copy of existing project including the baseline.
Hi Rodel, nice to chat with you again and thank you for your reply however, when looking at these settings (pic attached), I am understanding that the delete function is directly relating to the Activity. Am I misunderstanding the Oracle instructions?
So even though I have selected Update the Activity and checkboxed Delete (if not in new import) the activities that should be deleted (identified by running Visualiser comparison beforehand), are not being deleted.
Hi Rodel, nice to chat with you again and thank you for your reply however, when looking at these settings (pic attached), I am understanding that the delete function is directly relating to the Activity. Am I misunderstanding the Oracle instructions?
Hi Rodel, nice to chat with you again and thank you for your reply however, when looking at these settings (pic attached), I am understanding that the delete function is directly relating to the Activity. Am I misunderstanding the Oracle instructions?
[[wysiwyg_imageupload:8661:]]
Member for
19 years
Member for19 years
Submitted by Rodel Marasigan on Tue, 2024-04-30 14:11
Please note that the Delete field applies only to relationships with external projects, thresholds, activities, activity relationships, and activity resource assignments. Global data types are not affected by this setting.
Member for
19 yearsHi Rod,Yes, you are correct.
Hi Rod,
Yes, you are correct. The selected items are activity-related and will be automatically deleted if they are not found in the new record import and it works on me.
Another option you can choose is to use the 'Replace Existing Project' import action instead of selecting 'Update existing Project'. This will provide an exact copy of the imported Project.
Please Note: this import action will delete the whole copy of existing project including the baseline.
Member for
13 years 4 monthsHi Rodel, nice to chat with
Hi Rodel, nice to chat with you again and thank you for your reply however, when looking at these settings (pic attached), I am understanding that the delete function is directly relating to the Activity. Am I misunderstanding the Oracle instructions?
So even though I have selected Update the Activity and checkboxed Delete (if not in new import) the activities that should be deleted (identified by running Visualiser comparison beforehand), are not being deleted.
[[wysiwyg_imageupload:8661:]]S
Member for
13 years 4 monthsHi Rodel, nice to chat with
Hi Rodel, nice to chat with you again and thank you for your reply however, when looking at these settings (pic attached), I am understanding that the delete function is directly relating to the Activity. Am I misunderstanding the Oracle instructions?
[[wysiwyg_imageupload:8661:]]
Member for
13 years 4 monthsHi Rodel, nice to chat with
Hi Rodel, nice to chat with you again and thank you for your reply however, when looking at these settings (pic attached), I am understanding that the delete function is directly relating to the Activity. Am I misunderstanding the Oracle instructions?
[[wysiwyg_imageupload:8661:]]
Member for
19 yearsHi Rod,Please note that the
Hi Rod,
Please note that the Delete field applies only to relationships with external projects, thresholds, activities, activity relationships, and activity resource assignments. Global data types are not affected by this setting.