Thanks you for your reply and interesting suggestion. Master <=== Main project + (External ) Minor project. So both project will be on 1 schedule and roll up. Nice idea. I suppose you just maintain Main and Minor Project separately.
If you add an external project, it will just show up as extra tasks in your main project. Everything will roll up. If you don't want that, you may want to created a higher level master project and roll both your main project and this external project into it.
Member for
13 years 11 monthsMatt,Thanks you for your
Matt,
Thanks you for your reply and interesting suggestion. Master <=== Main project + (External ) Minor project. So both project will be on 1 schedule and roll up. Nice idea. I suppose you just maintain Main and Minor Project separately.
Member for
13 years 8 monthsKenneth, If you add an
Kenneth,
If you add an external project, it will just show up as extra tasks in your main project. Everything will roll up. If you don't want that, you may want to created a higher level master project and roll both your main project and this external project into it.
--Matt