How does OPP 3.2 Exter projects work within the main project schedule?

Member for

13 years 11 months

Matt,

Thanks you for your reply and interesting suggestion. Master <=== Main project + (External ) Minor project. So both project will be on 1 schedule and roll up. Nice idea. I suppose you just maintain Main and Minor Project separately.

Member for

13 years 8 months

Kenneth,

If you add an external project, it will just show up as extra tasks in your main project. Everything will roll up.  If you don't want that, you may want to created a higher level master project and roll both your main project and this external project into it.

--Matt