Vladimir, perhaps it could help if istead of "allow performance interruptions ..." it reads "restrict performance interruptions ..." as to make it easier to find the parameter code/name for reports.
Member for
24 years 8 months
Member for24 years9 months
Submitted by Vladimir Liberzon on Sat, 2022-03-26 17:11
Non-work calendar time does not split an activity. If an activity calendar is 8 hours per day and it works for five days it does not mean activity is split.
- In this sample schedule we have an availability of 10,000 ea. resources D1 except for the time span shutdown is scheduled where availability is set to 0.
- We use time resource production as to make D1 unavailable during shutdown and assign one unit to each activity that you do not want to stop work during shutdown but to be 100% scheduled before the shutdown or 100% after the shutdown.
- If using Microsoft Project try adjusting units of effort availability under resource information.
Member for
22 years 9 monthsThank you Raphaël and
Thank you Raphaël and Vladimir for your help
Alexandre
Member for
21 years 8 monthsThanks Vladimir, it is way
Thanks Vladimir, it is way easier but perhaps only available for Spider users. Now this approach is on my list of Spider scheduling strategies.
Both yields different results, choose the one/combination that best meets your requirements.
Member for
24 years 8 monthsThank you Rafael,we'll change
Thank you Rafael,
we'll change this in the new version.
Member for
21 years 8 monthsVladimir, perhaps it could
Vladimir, perhaps it could help if istead of "allow performance interruptions ..." it reads "restrict performance interruptions ..." as to make it easier to find the parameter code/name for reports.
Member for
24 years 8 monthsYes Rafael, you are right,
Yes Rafael, you are right, this is Spider Project option like many others absent in other tools.
Member for
24 years 8 monthsAlexanre,in Spider Project
Alexanre,
in Spider Project you can set that activity interruption is allowed for not more than N days.
In this case such activities will be automatically delayed to the next "window" if they could not be completed in the current "window".
Member for
21 years 8 monthsNon-work calendar time does
Non-work calendar time does not split an activity. If an activity calendar is 8 hours per day and it works for five days it does not mean activity is split.
- In this sample schedule we have an availability of 10,000 ea. resources D1 except for the time span shutdown is scheduled where availability is set to 0.
- We use time resource production as to make D1 unavailable during shutdown and assign one unit to each activity that you do not want to stop work during shutdown but to be 100% scheduled before the shutdown or 100% after the shutdown.
- If using Microsoft Project try adjusting units of effort availability under resource information.
Good luck.