Hi Pranab,

the easiest way is to copy Baseline_X to Interim Plan_X; then to set a new Baseline_X, it will replace the former one

the difference between Baseline and Interim Plan is: Interim Plan only saves Start and Finish Dates, not Work and Cost.

if you want to save both Start/Finish and Work/cost, create a new table with Custom fiels for all these 4 original fields (Date, Work, Cost) ; then copy and paste the Baseline fields to this new table

************

to answer your second question, I know no way to automatically set to 0 the Cost and Work fields in either the original schedule or the baseline in MSP; when I have to do this, I relly on the "Del" key on my computer keyboard!

Cheers

Alexandre