MS Project 2016 - Is there a way of changing the relationship of a group of selected activities from FS to SS

Member for

18 years 9 months

thanks Very much Bogdan

Member for

13 years 2 months

Show predecessor and succesor columns, copy paste in excel, delete the values from ms project, find and replace in excel FS with SS copy paste back in MS Project.