Total Float not calculating correctly

Member for

18 years 11 months

Here's how you get what you want:  as Alexandre suggests, apply a SNET (or better a FNET) constraint of 18May'22 to ID6.  Then also apply a Deadline=18May'22 to ID6.  (Use a clocktime format so you can confirm the time of day is the same for both.) The result will be TS=0 on ID6 and TS=3d on ID47.

Here your ID6 is a "Contract Date Milestone" for PAT complete.  I would also recommend a separate "Forecast Date Milestone" for PAT complete - logically inserted between ID47 and ID6, but with no constraint or deadline.

Good luck, tom  

Member for

13 years 1 month

OKay i did do that. But then the date become 18MAY but the float becomes 8 days. I am guessing its calculating the float from the end date of the project which is 27MAY2022

Member for

22 years 9 months

Hello,

I don't understand why you put a FNLT constraint on activityy #6;

try a Start No Earlier Than instead and set the date on May 18th

Alexandre