How to show client delays to project in Ghantt chart & alternatively claim for lost time.

Member for

19 years 10 months

Hi Timothy

You must still show the delay effect of the late delivery of the light fittings on the future progess of the work.

Show the employers delay period in a task bar on the installation of the lighting and impact the end date.

Report the rolling delay every week with contractual notices.

You may have been premature in getting the scaffold up early but that is different discussion.

Best regards

Mike T.

Member for

10 years

That seems like good,logical advice. I'll take it as a lesson learned for the future. Just another one of life's lessons!!.

 

Thank you. 

Member for

18 years 11 months

Timothy,
As the contractor, you have a duty (ethically and according to typical contract terms) to a) notify the Owner of the delay, and b) mitigate the delay to the maximum extent practicable. Burying delay events in your schedule for later digging up as part of a claim seems to go against these obligations.
Responsibility for the delaying event is assigned outside of the schedule control process. The consequences of the delaying event can be analyzed using a well developed and updated schedule. This can be more difficult to do in MSP than in other tools. As a novice, I would not advise you to be optimistic regarding your chances.