Gantt chart and resource allocation

Member for

8 years 8 months

Thank you for your answer Tom.

I think you are right since I've spent quite some hours to find a solution. Was hoping to manage without Excel, but there seems no other way to solve this.

 

Regards Fredrik

Member for

18 years 11 months

Hi Fredrik,

I have no answer for you.  Task Usage and Resource Usage have very few formatting options.  Summarizing the assignments is not among them.  I typically do this kind of work after exporting to Excel.

Good luck, tom