"Set Baseline" in MSP stores task and resource information, but not logic/relationships or float. Since it is not possible to recover any logic from a stored baseline, you can't recover the baseline critical path. Best practice is to save a separate mpp file of the baseline project.
Member for
18 years 11 monthsSorry Siddharth,"Set
Sorry Siddharth,
"Set Baseline" in MSP stores task and resource information, but not logic/relationships or float. Since it is not possible to recover any logic from a stored baseline, you can't recover the baseline critical path. Best practice is to save a separate mpp file of the baseline project.
Good luck, tom