First, why add those extra columns into the entry table, which is already designed to be just fine as it is, when you have table called the tracking table which has the fields you want already in it?
Display the status date on the chart as a vertical red line (gridlines).
It is incorrect to type in either the % complete or the % work complete. Stop doing that. Both fields are for MSP to calculate. Input actual start, actual duration, actual finish if task is finished. If task is not finished, move incomplete parts to status date.
If it is actual duration, check your Status Date time and your default calendar start time. E.g. if your Status Date is 11-Jan-16 00:00 and your default calendar start time is 08:00, you will get actual durations in fractions.
I am using MS project 2010 and I wanted to update the project so I added a base line to save the initial planning and then I started to add two columns of Actual start and actual finish dates
i added also status date to the work so I can rescedule the work and then I started to add the precentage of completed works for each task
Then after I pressed the button reschedule the tasks the completed tasks remained before the status date and the uncompleted task moved after the status date
now so far so good but the duration changed to fraction I tried to go to option and to schedule tab and changed the task to fixed duration and uncheck the new tasks are effort driven
Member for
19 years 11 monthsFirst, why add those extra
First, why add those extra columns into the entry table, which is already designed to be just fine as it is, when you have table called the tracking table which has the fields you want already in it?
Display the status date on the chart as a vertical red line (gridlines).
It is incorrect to type in either the % complete or the % work complete. Stop doing that. Both fields are for MSP to calculate. Input actual start, actual duration, actual finish if task is finished. If task is not finished, move incomplete parts to status date.
Any help?
Member for
21 years 9 monthsAhmed,Your question is a
Ahmed,
Your question is a little bit unclear.
Is it Actual Duration that changes to fraction?
If it is actual duration, check your Status Date time and your default calendar start time. E.g. if your Status Date is 11-Jan-16 00:00 and your default calendar start time is 08:00, you will get actual durations in fractions.
=jerome
Member for
18 years 9 monthsHi guysI am using MS project
Hi guys
I am using MS project 2010 and I wanted to update the project so I added a base line to save the initial planning and then I started to add two columns of Actual start and actual finish dates
i added also status date to the work so I can rescedule the work and then I started to add the precentage of completed works for each task
Then after I pressed the button reschedule the tasks the completed tasks remained before the status date and the uncompleted task moved after the status date
now so far so good but the duration changed to fraction I tried to go to option and to schedule tab and changed the task to fixed duration and uncheck the new tasks are effort driven
but still the same
any help??!!