Microsoft Project Member for 24 years 6 months Member for 24 years 7 months Submitted by Paul Harris on Thu, 2014-09-25 11:13 Permalink The % Complete is % Duration The % Complete is % Duration and will sunmmerise at Summary Levle based on the proportion of the total Actual Durations over the total of durations. The Physical % Does not summerise. This leaves % Work, so you would have to assign resources or you could do something with Custom Fields and formulae. Regards Paul E Harris BSc Hons, Certified Cost Engineer, PRINCE2 Practitioner Managing Director and President Eastwood Harris Pty Ltd, Australia http://www.eh.com.au, http://www.primavera.com.auand http://eastwoodharris.com. Project Control Consultants and Planning and scheduling software book and training material publishers Primavera P6 Version 8.3 eLearning available from http://www.primaskills.com.au/project-management-training/ Log in or register to post comments
Member for 24 years 6 months Member for 24 years 7 months Submitted by Paul Harris on Thu, 2014-09-25 11:13 Permalink The % Complete is % Duration The % Complete is % Duration and will sunmmerise at Summary Levle based on the proportion of the total Actual Durations over the total of durations. The Physical % Does not summerise. This leaves % Work, so you would have to assign resources or you could do something with Custom Fields and formulae. Regards Paul E Harris BSc Hons, Certified Cost Engineer, PRINCE2 Practitioner Managing Director and President Eastwood Harris Pty Ltd, Australia http://www.eh.com.au, http://www.primavera.com.auand http://eastwoodharris.com. Project Control Consultants and Planning and scheduling software book and training material publishers Primavera P6 Version 8.3 eLearning available from http://www.primaskills.com.au/project-management-training/
Member for
24 years 6 monthsThe % Complete is % Duration
The % Complete is % Duration and will sunmmerise at Summary Levle based on the proportion of the total Actual Durations over the total of durations.
The Physical % Does not summerise.
This leaves % Work, so you would have to assign resources or you could do something with Custom Fields and formulae.
Regards
Paul E Harris
BSc Hons, Certified Cost Engineer, PRINCE2 Practitioner
Managing Director and President
Eastwood Harris Pty Ltd, Australia
http://www.eh.com.au, http://www.primavera.com.auand http://eastwoodharris.com.
Project Control Consultants and Planning and scheduling software book and training material publishers
Primavera P6 Version 8.3 eLearning available from http://www.primaskills.com.au/project-management-training/