Updating Schedule

Member for

11 years 5 months

Dear planners,

I rescheduled my project, the new finish time change when I update project. how can I update rescheduled project in MSP?

 

 Best regards,

hasanzadeh

Member for

21 years 10 months

Thanks Li,

This way is manually updated, it does not make sense, what I need is; the schedule should be automatically updated once the actual dates and percentage complete are entered.

Regards,

Moutaz

Member for

11 years 6 months

I can share some ways that I always use . i am a new guy to MSP,but you can have a try.

after you typing into the percentage in the complete coloum , you can add another coloum called "remain duration", and type into you estimated remain duration. the finish date will change.