This way is manually updated, it does not make sense, what I need is; the schedule should be automatically updated once the actual dates and percentage complete are entered.
I can share some ways that I always use . i am a new guy to MSP,but you can have a try.
after you typing into the percentage in the complete coloum , you can add another coloum called "remain duration", and type into you estimated remain duration. the finish date will change.
Member for
11 years 5 monthsDear planners,I rescheduled
Dear planners,
I rescheduled my project, the new finish time change when I update project. how can I update rescheduled project in MSP?
Best regards,
hasanzadeh
Member for
21 years 10 monthsThanks Li,This way is
Thanks Li,
This way is manually updated, it does not make sense, what I need is; the schedule should be automatically updated once the actual dates and percentage complete are entered.
Regards,
Moutaz
Member for
11 years 6 monthsI can share some ways that I
I can share some ways that I always use . i am a new guy to MSP,but you can have a try.
after you typing into the percentage in the complete coloum , you can add another coloum called "remain duration", and type into you estimated remain duration. the finish date will change.