I do not have project 2007, but I could not reproduce the behavior, described by you with MS Project 2010. The behavior I observed is as follows:
It is not possible to change actual cost until activity is 100% complete. The actual cost in this case is calculated by the formula Actual Cost=Activity Cost*%complete
After activity is 100% complete, one can change actual cost and it does not change activity duration
The task is fixed work and effort driven. I have assigend work resource and cost resource. I didnt assign material resource. I entered the material value as a cost resource for the activity.
The task is fixed work and effort driven. I have assigend work resource and cost resource. I didnt assign material resource. I entered the material value as a cost resource for the activity.
Thanks in advance,
Regards,
Bala
Member for
14 years 8 months
Member for14 years9 months
Submitted by Baiju Jayswal on Fri, 2014-01-24 07:12
can you say what is the task type. Is it Fixed duration, fixed unit or Fixed work. another thing you have have to check that the activity is effort driven or not. Have you enter material resource.
Regards\\
Member for
14 years 8 months
Member for14 years9 months
Submitted by Baiju Jayswal on Fri, 2014-01-24 07:12
can you say what is the task type. Is it Fixed duration, fixed unit or Fixed work. another thing you have have to check that the activity is effort driven or not. Have you enter material resource.
Member for
12 years 3 monthsEvgeny, Yes, you
Evgeny,
Yes, you are right. Thanks for your help...
Regards,
Bala
Member for
17 years 9 monthsBala,I do not have project
Bala,
I do not have project 2007, but I could not reproduce the behavior, described by you with MS Project 2010. The behavior I observed is as follows:
Regards.
Evgeny
Member for
12 years 3 monthsHi kumar, The
Hi kumar,
The task is fixed work and effort driven. I have assigend work resource and cost resource. I didnt assign material resource. I entered the material value as a cost resource for the activity.
Thanks in advance,
Regards,
Bala
Member for
12 years 3 monthsHi kumar, The
Hi kumar,
The task is fixed work and effort driven. I have assigend work resource and cost resource. I didnt assign material resource. I entered the material value as a cost resource for the activity.
Thanks in advance,
Regards,
Bala
Member for
14 years 8 monthsHi bala can you say what is
Hi bala
can you say what is the task type. Is it Fixed duration, fixed unit or Fixed work. another thing you have have to check that the activity is effort driven or not. Have you enter material resource.
Regards\\
Member for
14 years 8 monthsHi bala can you say what is
Hi bala
can you say what is the task type. Is it Fixed duration, fixed unit or Fixed work. another thing you have have to check that the activity is effort driven or not. Have you enter material resource.
Regards\\