Gantt Chart bars on wrong dates

Member for

19 years 10 months

Hi Craig

Do the milestones have both Predecessor and Successor Logic?

If no Predessor you can try setting the position as ALAP - if no Successor then you will have to fix it with a constraint which is bad planning practice but needed soemtimes for presentation purposes.

Best regards

Mike Testro

Member for

13 years 9 months

I should add that it is actually only for milestones that are disappearing from the Gantt Chart, not activities with durations.

Logic lines appear on the screen (going back to 1984), but when printed these links disappear completely, meaning the unitiated have to have it explained that logic does exist, it is just not showing for some unknown reason.