Microsoft Project Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Thu, 2013-09-05 18:53 Permalink Hi PaulIn the project start Hi Paul In the project start dialogue for each project there should be a field for Project Manager - or at least a field that can be adapted for that purpose. There is no quick way but to enter the name of the project manager for each project. The contents should then be displayed in your chart. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Thu, 2013-09-05 18:53 Permalink Hi PaulIn the project start Hi Paul In the project start dialogue for each project there should be a field for Project Manager - or at least a field that can be adapted for that purpose. There is no quick way but to enter the name of the project manager for each project. The contents should then be displayed in your chart. Best regards Mike Testro
Member for
19 years 10 monthsHi PaulIn the project start
Hi Paul
In the project start dialogue for each project there should be a field for Project Manager - or at least a field that can be adapted for that purpose.
There is no quick way but to enter the name of the project manager for each project.
The contents should then be displayed in your chart.
Best regards
Mike Testro