Microsoft Project Member for 16 years 4 months Member for 16 years 4 months Submitted by M. Kamel Bessekri on Sat, 2013-07-06 17:54 Permalink AlexandreI have discovered it Alexandre I have discovered it , Thanks to have confirm it . Regards KAmel Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Sat, 2013-07-06 17:19 Permalink Kamel,there is no need to wbs Kamel, there is no need to wbs sumamry in MS Project, as it is possible to assigne resources to summary tasks Alexandre Log in or register to post comments
Member for 16 years 4 months Member for 16 years 4 months Submitted by M. Kamel Bessekri on Sat, 2013-07-06 17:54 Permalink AlexandreI have discovered it Alexandre I have discovered it , Thanks to have confirm it . Regards KAmel
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Sat, 2013-07-06 17:19 Permalink Kamel,there is no need to wbs Kamel, there is no need to wbs sumamry in MS Project, as it is possible to assigne resources to summary tasks Alexandre
Member for
16 years 4 monthsAlexandreI have discovered it
Alexandre
I have discovered it , Thanks to have confirm it .
Regards
KAmel
Member for
22 years 9 monthsKamel,there is no need to wbs
Kamel,
there is no need to wbs sumamry in MS Project, as it is possible to assigne resources to summary tasks
Alexandre