Microsoft Project Member for 13 years 1 month Member for 13 years 1 month Submitted by Mahzaj on Sun, 2013-04-07 07:52 Permalink Dear Jack, What Dear Jack, What i would like to know is that when adding a task duration ie: no. of days should we also include the holidays and weekends too. Regards, Mahzaj Member for 13 years 1 month Member for 13 years 1 month Submitted by Mahzaj on Sun, 2013-04-07 07:52 Permalink Dear Jack, What Dear Jack, What i would like to know is that when adding a task duration ie: no. of days should we also include the holidays and weekends too. Regards, Mahzaj Member for 21 years 6 months Member for 21 years 6 months Submitted by Jack Black on Tue, 2013-04-02 04:15 Permalink By default, Microsoft Project By default, Microsoft Project does NOT include weekends within the input Duration. You can find more insight on Duration and Microsoft Project from here: http://www.pmconnection.com/modules.php?name=Web_Links&l_op=search&query=duration&orderby=hitsD Hope this helps! Log in or register to post comments
Member for 13 years 1 month Member for 13 years 1 month Submitted by Mahzaj on Sun, 2013-04-07 07:52 Permalink Dear Jack, What Dear Jack, What i would like to know is that when adding a task duration ie: no. of days should we also include the holidays and weekends too. Regards, Mahzaj
Member for 13 years 1 month Member for 13 years 1 month Submitted by Mahzaj on Sun, 2013-04-07 07:52 Permalink Dear Jack, What Dear Jack, What i would like to know is that when adding a task duration ie: no. of days should we also include the holidays and weekends too. Regards, Mahzaj
Member for 21 years 6 months Member for 21 years 6 months Submitted by Jack Black on Tue, 2013-04-02 04:15 Permalink By default, Microsoft Project By default, Microsoft Project does NOT include weekends within the input Duration. You can find more insight on Duration and Microsoft Project from here: http://www.pmconnection.com/modules.php?name=Web_Links&l_op=search&query=duration&orderby=hitsD Hope this helps!
Member for
13 years 1 monthDear Jack, What
Dear Jack,
What i would like to know is that when adding a task duration ie: no. of days should we also include the holidays and weekends too.
Regards,
Mahzaj
Member for
13 years 1 monthDear Jack, What
Dear Jack,
What i would like to know is that when adding a task duration ie: no. of days should we also include the holidays and weekends too.
Regards,
Mahzaj
Member for
21 years 6 monthsBy default, Microsoft Project
By default, Microsoft Project does NOT include weekends within the input Duration. You can find more insight on Duration and Microsoft Project from here:
http://www.pmconnection.com/modules.php?name=Web_Links&l_op=search&query=duration&orderby=hitsD
Hope this helps!