Microsoft Project Member for 17 years 9 months Member for 17 years 10 months Submitted by Evgeny Z. on Sat, 2013-01-19 22:11 Permalink Ncube,1) You need to switch Ncube, 1) You need to switch off Automatic Resource Leveling (in MSP 2007 Tools=>Resource Leveling => Manual). 2) MS Project seem to show correctly all work-related values in summary task See below Log in or register to post comments
Member for 17 years 9 months Member for 17 years 10 months Submitted by Evgeny Z. on Sat, 2013-01-19 22:11 Permalink Ncube,1) You need to switch Ncube, 1) You need to switch off Automatic Resource Leveling (in MSP 2007 Tools=>Resource Leveling => Manual). 2) MS Project seem to show correctly all work-related values in summary task See below
Member for
17 years 9 monthsNcube,1) You need to switch
Ncube,
1) You need to switch off Automatic Resource Leveling (in MSP 2007 Tools=>Resource Leveling => Manual).
2) MS Project seem to show correctly all work-related values in summary task
See below