Microsoft Project Member for 17 years 9 months Member for 17 years 10 months Submitted by Evgeny Z. on Thu, 2012-12-20 12:28 Permalink Kamel,I normally go to Kamel, I normally go to resource usage view, select required data on the right side, copy it (Cntrl +C) and then paste it in Excel. I did not try to see, if it can be exported via report. Regards. Evgeny Log in or register to post comments
Member for 17 years 9 months Member for 17 years 10 months Submitted by Evgeny Z. on Thu, 2012-12-20 12:28 Permalink Kamel,I normally go to Kamel, I normally go to resource usage view, select required data on the right side, copy it (Cntrl +C) and then paste it in Excel. I did not try to see, if it can be exported via report. Regards. Evgeny
Member for
17 years 9 monthsKamel,I normally go to
Kamel,
I normally go to resource usage view, select required data on the right side, copy it (Cntrl +C) and then paste it in Excel.
I did not try to see, if it can be exported via report.
Regards.
Evgeny