The project calendar is "standard". actually, it isn't. or rather, the standard calendar has been changed to be 7d x 10.5h.
You should copy this calendar and give the copy an appropriate name such as "AA 7d x 10.5h". Then recover the original standard calendar (5d x 8h) from the global template (tools, organizer).
Then assign your "AA 7d x 10.5h" as the project calendar.
Yes, assign the 24 hours calendar to all tasks which can run 24 hours.
Input the durations of those tasks in hours, not days, so that there is no need to rely on the conversion factor for hours/day.
You don't need either of the formulae for what you need to do.
Member for
13 years 9 monthsHi Trevor, I have don this
Hi Trevor, I have don this earlier on but my PM insist he wants to see the activities with 24 hrs in days, thats was the reason
Is there any work around to this please?
Thanks
Member for
19 years 11 monthsYour points one by one:The
Your points one by one:
The project calendar is "standard". actually, it isn't. or rather, the standard calendar has been changed to be 7d x 10.5h.
You should copy this calendar and give the copy an appropriate name such as "AA 7d x 10.5h". Then recover the original standard calendar (5d x 8h) from the global template (tools, organizer).
Then assign your "AA 7d x 10.5h" as the project calendar.
Yes, assign the 24 hours calendar to all tasks which can run 24 hours.
Input the durations of those tasks in hours, not days, so that there is no need to rely on the conversion factor for hours/day.
You don't need either of the formulae for what you need to do.