Microsoft Project Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Tue, 2012-09-04 09:45 Permalink Hi Bogdan,Baseline Cumulative Hi Bogdan, Baseline Cumulative Work cannot be displayed in MS Project tables nor Resource Graph; you will have to export the data to MS Excel and create the table and the curve there It is also possible to use a Visual Report Alexandre Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Tue, 2012-09-04 09:45 Permalink Hi Bogdan,Baseline Cumulative Hi Bogdan, Baseline Cumulative Work cannot be displayed in MS Project tables nor Resource Graph; you will have to export the data to MS Excel and create the table and the curve there It is also possible to use a Visual Report Alexandre
Member for
22 years 9 monthsHi Bogdan,Baseline Cumulative
Hi Bogdan,
Baseline Cumulative Work cannot be displayed in MS Project tables nor Resource Graph; you will have to export the data to MS Excel and create the table and the curve there
It is also possible to use a Visual Report
Alexandre