Physical Percent Complete cannot be linked to Actual / Remaining Duration
Only % Complete and Work % Complete can be unlinked from Actual Duration, they are linked by default
Task Duration type is being used by MSP to compute the task duration / resource assignment units / resource assignment work when you change a value in the assignment; it is not used when you update the project either manually or automatically
Member for
22 years 9 monthsJames,Physical Percent
James,
Physical Percent Complete cannot be linked to Actual / Remaining Duration
Only % Complete and Work % Complete can be unlinked from Actual Duration, they are linked by default
Task Duration type is being used by MSP to compute the task duration / resource assignment units / resource assignment work when you change a value in the assignment; it is not used when you update the project either manually or automatically
Alexandre