How to calculate % work done

Member for

22 years 9 months

Hi Ashik

display "Task Usage" view, the set the time scale to month, right-click the distribution panel (rightmost panel), and select the "Baseline Work" field

as MS Project does not have a "% planned work" field, you will have to compute the %tage by yourself

Alexandre