Microsoft Project Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Mon, 2012-07-09 18:43 Permalink Hi Ashikdisplay "Task Usage" Hi Ashik display "Task Usage" view, the set the time scale to month, right-click the distribution panel (rightmost panel), and select the "Baseline Work" field as MS Project does not have a "% planned work" field, you will have to compute the %tage by yourself Alexandre Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Mon, 2012-07-09 18:43 Permalink Hi Ashikdisplay "Task Usage" Hi Ashik display "Task Usage" view, the set the time scale to month, right-click the distribution panel (rightmost panel), and select the "Baseline Work" field as MS Project does not have a "% planned work" field, you will have to compute the %tage by yourself Alexandre
Member for
22 years 9 monthsHi Ashikdisplay "Task Usage"
Hi Ashik
display "Task Usage" view, the set the time scale to month, right-click the distribution panel (rightmost panel), and select the "Baseline Work" field
as MS Project does not have a "% planned work" field, you will have to compute the %tage by yourself
Alexandre