How to update multiple project plans together in Microsoft Project 2007

Member for

22 years 9 months

Gayatri,

I would agregate all my individual projects in a new "master project": Window, New, ...

then I would add appropriate links between tasks amongst the different individual projects; MS Project wil create links between the master project and the individual projects (almost like links between different sheets in a Excel workbook)

when you status task 1A in Project 1 and delay its End Date, its successor task 2B in Project 2 will be delayed too.

Note: it is not possible to save the baseline in the master project; go to each individual project to save each project baseline

Alexandre