Making Gantt chart and resource usage views independently viewable in MSP 2007

Member for

22 years 9 months

Hi proj2,

no, you can't have a combined view without the top one filtering the bottom one; this is built in MSP

the only way around, but not practical for big mpp's as you say, would be to select ALL the rows in the Gantt Chart; you would see in the bottom pane the project data filtered for ALL the selected rows

Alexandre