Summary Baseline costs and work are copied from cost and work fields when baseline is set. They are not calculated from their detail tasks. that is why the summary baseline costs and work will not recalculate when moving / adding/ deleting tasks from it.
Member for
13 years 7 monthsSummary Baseline costs and
Summary Baseline costs and work are copied from cost and work fields when baseline is set. They are not calculated from their detail tasks. that is why the summary baseline costs and work will not recalculate when moving / adding/ deleting tasks from it.