Moving Tasks from one Summary to another

Member for

13 years 7 months

Summary Baseline costs and work are copied from cost and work fields when baseline is set. They are not calculated from their detail tasks. that is why the summary baseline costs and work will not recalculate when moving / adding/ deleting tasks from it.

http://office.microsoft.com/video.aspx?assetid=ES010277624&vwidth=1024&vheight=768&CTT=11&Origin=

 

M.