A couple of initial remarks: 1) A milestone can only be 0% complete or 100% complete. Nothing in between. Milestone is defined as its duration and work being zero, so saying a milestone is 60% complete would just give the result 60% times zero which is still zero.
2) Secondly, you can't have uncompleted activities/milestones in the past, however, many people still prefer to see the progress (zig-zag) line, so let's forget about that for a while.
To answer your question you could make a formula for a flag field asking that if "Baseline Finish" is less than "Status Date" and "Actual Finish" equals "NA" then the flag field would turn "Yes" or something similar. Then make a red bar style incorporating that flag field. All bars for uncompleted activities that should have been completed according to the baseline will now automatically turn red.
You right click on that specific activity, you click on information,you go to the advanced tab,then on the bottom left you click to make that activity a milestone,
In your case your program is not updated and scheduled on milestone date, you need to update the activities on which this milestone was dependent on and after that when you will reschdule the program then the milestone will become 100%.
Member for
19 years 8 monthsYvonne, A couple of initial
Yvonne,
A couple of initial remarks: 1) A milestone can only be 0% complete or 100% complete. Nothing in between. Milestone is defined as its duration and work being zero, so saying a milestone is 60% complete would just give the result 60% times zero which is still zero.
2) Secondly, you can't have uncompleted activities/milestones in the past, however, many people still prefer to see the progress (zig-zag) line, so let's forget about that for a while.
To answer your question you could make a formula for a flag field asking that if "Baseline Finish" is less than "Status Date" and "Actual Finish" equals "NA" then the flag field would turn "Yes" or something similar. Then make a red bar style incorporating that flag field. All bars for uncompleted activities that should have been completed according to the baseline will now automatically turn red.
Regards,
Bo
Member for
13 years 9 monthsYou right click on that
You right click on that specific activity, you click on information,you go to the advanced tab,then on the bottom left you click to make that activity a milestone,
Hope you find it helful
Hlami
Member for
13 years 11 monthssimple trick, right click on
simple trick, right click on the milestone diamond and change its colour to red, though it is a manual trick but it will solve ur problem.
Member for
13 years 11 monthsThanks for the response but I
Thanks for the response but I want to be able to show the task is running late and have it highlighted in red.
Member for
13 years 11 monthsHi.In your case your program
Hi.
In your case your program is not updated and scheduled on milestone date, you need to update the activities on which this milestone was dependent on and after that when you will reschdule the program then the milestone will become 100%.
regards
kk