The standard practice is to save baseline after your schedule is perfect, before puting any actual.
Then u can update actuals and monitor the difference between plan v/s actual.
After the completion of project upto some %ge, u fill that there are noticable changes, which need to be edited in plan itself (like addition of scope or like modification / revision / rework), than you can copy paste actuals as baseline2 with neccessory additions.
Save baseline2 and than again start putting actuals. Monitor plan v/s actuals again...
Member for
12 years 6 monthsThe standard practice is to
The standard practice is to save baseline after your schedule is perfect, before puting any actual.
Then u can update actuals and monitor the difference between plan v/s actual.
After the completion of project upto some %ge, u fill that there are noticable changes, which need to be edited in plan itself (like addition of scope or like modification / revision / rework), than you can copy paste actuals as baseline2 with neccessory additions.
Save baseline2 and than again start putting actuals. Monitor plan v/s actuals again...