CONDITIONAL relationships

Member for

21 years 8 months

Beware resource leveling is somewhat limited for this purpose.

If the requirement is for any one of the selected activities having finished but not necessarily the other having even started you might need conditional logic as the link will exist only on one of the activities, link existence will depend on a condition. See the following link.

http://youtu.be/-9qmE282ins

Needless to say more complex scenarios for groups of activities that might happen or might not happen under certain conditions can only be modeled with conditional scheduling.

http://www.youtube.com/watch?v=A314H5ds7Xw

Best regards,

Rafael

I Think Therefore I Exist - RD

Member for

14 years 7 months

Dear Veladimir

Thank you So much. your solution was the best.

regards

Shima

Member for

24 years 9 months

Shima,

I already answered to your question.

Did you try an approach that I proposed?

Regards,

Vladimir

Member for

14 years 7 months

Dear SM PUM

now, I don't know which A or B will affect on start/ finish of C activity... I just know that after starting the project, A and B activities are parallel activities and if just one of A or B finish, C activity can start. now, how can define these relationships for C activity?

 

thanks

Shima

Member for

13 years 11 months

Shima Zabetian

If an activity has multiple predecessors then you have to look that which one of them is "driving" the successor activity.For Example if Activity" C" has Two Predessors "A" & "B" .Now if you want to link the activities so that "C "should be dependant on Finish/start  of " B" then you just need to make B as"Dricing" activity for "C".

I hope it makes sense.

Regards,

Member for

24 years 9 months

You can try this approach:

1) Create dummy resource R,

2) Set that there are only two units of resource R,

3) Assign one unit of R on all three activities,

4) Assign activity priorities (predecessors have higher priorities but do not link activities),

5) Run resource leveling (for resource R if there is a choice).

 

There is more reliable method that can be used in Spider Project but both MSP and P6 do not have necessary functionality.