How do i work with the MS-project full days?

Member for

19 years

Jose, try checking the calendars. There could be a day that has non-standard (or nonconsistent) working hours per day (or totally different hour of start and finish hour per day).

cheers!

 

Keyel

Member for

19 years

Jose, try checking the calendars. There could be a day that has non-standard (or nonconsistent) working hours per day (or totally different hour of start and finish hour per day).

cheers!

 

Keyel

Member for

14 years 1 month

Hi Mike,

 

I found onething that was making a half day. When we put in the predecessor 80TI-50% we break a day. The correct way to do not break the activities this is writing 80TI-20 if you have an odd number of duration activity.

But now i have another strange situation. In the field "total margin of delay" (i don't know if it's the correct form because my programm version is portuguese) it shows 563,89 days, not 564.

 

There's no activity starting in a half day.

 

Thanks.

 

José Otávio

Member for

19 years 10 months

Hi Jose

Perhaps your fist activity finishes at the middle of the day and all the rest follow.

Best regards

Mike Testro