Microsoft Project Member for 15 years Member for 15 years Submitted by akherief on Tue, 2011-11-08 09:49 Permalink Thank you Ali for the Thank you Ali for the confirmation. Member for 15 years 7 months Member for 15 years 7 months Submitted by Ali Deveboynu on Mon, 2011-10-31 15:31 Permalink % complete on summary task % complete on summary task are calculated by simple aritmetic average , assume you have 2 task under summary task , which has 10 and 20 days durations and %40 and %50 completes , % complete calculates such as (40*10)+(50*20)/30 best regards Log in or register to post comments
Member for 15 years Member for 15 years Submitted by akherief on Tue, 2011-11-08 09:49 Permalink Thank you Ali for the Thank you Ali for the confirmation.
Member for 15 years 7 months Member for 15 years 7 months Submitted by Ali Deveboynu on Mon, 2011-10-31 15:31 Permalink % complete on summary task % complete on summary task are calculated by simple aritmetic average , assume you have 2 task under summary task , which has 10 and 20 days durations and %40 and %50 completes , % complete calculates such as (40*10)+(50*20)/30 best regards
Member for
15 yearsThank you Ali for the
Thank you Ali for the confirmation.
Member for
15 years 7 months% complete on summary task
% complete on summary task are calculated by simple aritmetic average , assume you have 2 task under summary task , which has 10 and 20 days durations and %40 and %50 completes , % complete calculates such as (40*10)+(50*20)/30
best regards