Microsoft Project Member for 14 years 1 month Member for 14 years 1 month Submitted by alex mclellan on Mon, 2011-10-03 12:34 Permalink unfortunately i need to unfortunately i need to relevel my resources regularly. thanks anyway alex Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Mon, 2011-10-03 12:13 Permalink Hi Alex Use a single FS link Hi Alex Use a single FS link between Task A and B. Then set task A ALAP. If you allow the software to level your resources then it will over ride any logic that you have previously set up. That is why it should never be used. Best regards Mike Testro Log in or register to post comments
Member for 14 years 1 month Member for 14 years 1 month Submitted by alex mclellan on Mon, 2011-10-03 12:34 Permalink unfortunately i need to unfortunately i need to relevel my resources regularly. thanks anyway alex
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Mon, 2011-10-03 12:13 Permalink Hi Alex Use a single FS link Hi Alex Use a single FS link between Task A and B. Then set task A ALAP. If you allow the software to level your resources then it will over ride any logic that you have previously set up. That is why it should never be used. Best regards Mike Testro
Member for
14 years 1 monthunfortunately i need to
unfortunately i need to relevel my resources regularly. thanks anyway
alex
Member for
19 years 10 monthsHi Alex Use a single FS link
Hi Alex
Use a single FS link between Task A and B.
Then set task A ALAP.
If you allow the software to level your resources then it will over ride any logic that you have previously set up.
That is why it should never be used.
Best regards
Mike Testro