Working Dates Back in Project 2003

Member for

21 years 8 months

The procedure of assigning ALAP constraint is no good as it will make all activities critical.

In MS Project Schedule from Finish Date shall do it, just be careful with date constraints.

If your software do not provide for a backward computation that keeps finish date fixed and display float then try fixing the project finish date to your target date. Perform a schedule run and find the Early and Late dates for Start milestone. If you are performing resource leveling remember to perform the constrained schedule using the resource leveling option. Then delete finish constraint and set DD to the Early Start of the Start Milestone you just got if the target date was moved backwards or use Late Start if project target finish was moved forward.

Even when my software provides backward computation functionality out of the box I have never been in need to use this functionality on a real schedule with intermediate date constraints. It would be interesting to see how intermediate date constraints perform as this can create some issues if you do not move them back or forward as target finish date is moved back or forward. Suggest using some logic as to keep intermediate milestone dates in control.

Member for

15 years 8 months

You're welcome.

--Ismet

Member for

16 years 7 months

Thinking about it, another and probably better option would be to display the bar & columns for your late dates rather than making everything ALAP.

 

This gives you the option of applying other constraints to activities if required, and means you don't loose the early dates which may still be handy to know.

Member for

14 years 4 months

Thanks Gary, I'm going to use this method on another project I've got coming up soon - cheers.

Mark

Member for

14 years 4 months

Thanks Ismet, this worked a treat. I appreciate your help.

Mark

Member for

15 years 8 months

Planning from the Finish date is the most practical way to do backward scheduling. Project will automatically set all the new tasks with default constraint As Late As Possible (ALAP). You can set backward scheduling as follows: Project menu | Project Information... command > Project Information for ... Dialog Box | Schedule from: <select Project Finish Date> | OK

Member for

16 years 7 months

Create your schedule as normal, constrain your given delivery date, and set all other tasks as ALAP.