Microsoft Project Member for 14 years 6 months Member for 14 years 6 months Submitted by billdrew160 on Wed, 2012-08-22 20:09 Permalink Primavera is not compatible Primavera is not compatible with MSP 2007. You must save your MSP either as MSP 2003 or as an XML file and then import it into P4. Log in or register to post comments