Microsoft Project Member for 18 years 4 months Member for 18 years 4 months Submitted by John Banks on Mon, 2011-01-31 13:03 Permalink thanks for that thanks for that Member for 17 years 9 months Member for 17 years 9 months Submitted by Darren Kosa on Fri, 2011-01-28 22:39 Permalink Hi John, By ghost task do you Hi John, By ghost task do you mean an external task? If you do, I think there is an external task column you can insert and then filter on. Regards, Darren Log in or register to post comments
Member for 18 years 4 months Member for 18 years 4 months Submitted by John Banks on Mon, 2011-01-31 13:03 Permalink thanks for that thanks for that
Member for 17 years 9 months Member for 17 years 9 months Submitted by Darren Kosa on Fri, 2011-01-28 22:39 Permalink Hi John, By ghost task do you Hi John, By ghost task do you mean an external task? If you do, I think there is an external task column you can insert and then filter on. Regards, Darren
Member for
18 years 4 monthsthanks for that
thanks for that
Member for
17 years 9 monthsHi John, By ghost task do you
Hi John,
By ghost task do you mean an external task?
If you do, I think there is an external task column you can insert and then filter on.
Regards,
Darren