at the difference of P3, MSP does not create the baseline as a second project; it does copy and paste the fields: Start, Finish, Work and Cost to Baseline Start, Baseline Finish, ...
therefore, if you had not saved the baseline before the 1st update of the project, there is no way to restore it.
Member for
22 years 9 monthsRE: restore baseline
Trevor,
good work-around!
I would copy the actual data in a Excel sheet 1st of all!
Alexandre
Member for
19 years 11 monthsRE: restore baseline
How about select all tasks, strip off all progress, save baseline, re-input all progress?
Member for
22 years 9 monthsRE: restore baseline
Jack,
at the difference of P3, MSP does not create the baseline as a second project; it does copy and paste the fields: Start, Finish, Work and Cost to Baseline Start, Baseline Finish, ...
therefore, if you had not saved the baseline before the 1st update of the project, there is no way to restore it.
Alexandre