Microsoft Project Member for 19 years 11 months Member for 19 years 11 months Submitted by Trevor Rabey on Mon, 2010-01-11 18:56 Permalink RE: Indent/Outdent of activities in MS Project It looks self explanatory, doesnt it? Look at the task that you are about to make into a heading by indenting the other tasks under it. It will have predecessors and/or successors. Remove them. Now indent the other tasks and it will be ok. You cannot have a task whose predecessor or successor is its own heading. It would be like linking a task to itself. Log in or register to post comments
Member for 19 years 11 months Member for 19 years 11 months Submitted by Trevor Rabey on Mon, 2010-01-11 18:56 Permalink RE: Indent/Outdent of activities in MS Project It looks self explanatory, doesnt it? Look at the task that you are about to make into a heading by indenting the other tasks under it. It will have predecessors and/or successors. Remove them. Now indent the other tasks and it will be ok. You cannot have a task whose predecessor or successor is its own heading. It would be like linking a task to itself.
Member for
19 years 11 monthsRE: Indent/Outdent of activities in MS Project
It looks self explanatory, doesnt it?
Look at the task that you are about to make into a heading by indenting the other tasks under it.
It will have predecessors and/or successors.
Remove them.
Now indent the other tasks and it will be ok.
You cannot have a task whose predecessor or successor is its own heading. It would be like linking a task to itself.