Activity strech

Member for

22 years 9 months

Assaf,

SS and FF links do not work to build a hammock activity in MSP; you will have to use copye / special paste instead:

a) copy B’s start date and paste it with a link to A’s

b) copy C’s finish date and paste it with a link to A’s

3) add SS and FF links if you wish, but they are not necessary, they will only make you show the "purely logical" relationships between tasks, I mean they demonstrate relationships to the reader

Alexandre

Member for

19 years 11 months

Your question has already been answered at microsoft.public.project