Microsoft Project Member for 17 years 9 months Member for 17 years 9 months Submitted by Darren Kosa on Mon, 2009-02-23 06:43 Permalink RE: SCURVE COMPARISON Hi Solo, For MS Project 2k3, use the ‘Analyze Timescaled Data in Excel’ wizard and then chart it using Excel. For MS Project 2k7, there should already be a visual report(s) that you can use. Regards, Darren Log in or register to post comments
Member for 17 years 9 months Member for 17 years 9 months Submitted by Darren Kosa on Mon, 2009-02-23 06:43 Permalink RE: SCURVE COMPARISON Hi Solo, For MS Project 2k3, use the ‘Analyze Timescaled Data in Excel’ wizard and then chart it using Excel. For MS Project 2k7, there should already be a visual report(s) that you can use. Regards, Darren
Member for
17 years 9 monthsRE: SCURVE COMPARISON
Hi Solo,
For MS Project 2k3, use the ‘Analyze Timescaled Data in Excel’ wizard and then chart it using Excel.
For MS Project 2k7, there should already be a visual report(s) that you can use.
Regards,
Darren