Milestones ignore calendars in Project 2007

Member for

22 years 9 months

Niek,

who knows, it’s so easy to make a mistake...

well, I don’t know; I could send you my file if you want, just give me your email.

Alexandre

Member for

20 years 7 months

Hi Alex, Tout va bien?



12.0.6211.1000 / SP1 MSO 12.0.6320.5000



Assigning resources to milestones, what do you take me for? :-)



Cheers,



Niek.

Member for

22 years 9 months

Niek,

Which release of MSP 2007 are you working with?

I am using MSP2007 Pro Build 12.0.4518.1214 and everything is working fine.

You should check that you do not have any resource assigned to your milestone, or that the option "Scheduling ignores resource calendar" is active

Alexandre