Microsoft Project Member for 17 years 2 months Member for 17 years 2 months Submitted by Varun Ram on Tue, 2008-08-26 13:20 Permalink RE: MS Project Duration thanks Darren. I will check these settings. I posted the whole row. Member for 17 years 9 months Member for 17 years 9 months Submitted by Darren Kosa on Tue, 2008-08-26 12:57 Permalink RE: MS Project Duration Hi Varun, A few of the most likely causes for you to investigate are listed below: 1) Are the default calendar options the same in all the projects? (Tools > Options > Calendar) 2) Are the calendar working times the same? (Tools > Change Working Time) 3) Are the resource Base Calendars the same? (View > Resource Sheet) 4) Are the Task Calendars the same? (In the Gantt View – Insert > Column > Task Calendar) 5) Is the calculation mode set to automatic? (Tools > Options >Calculation) 6) Did you copy the whole row or just the activity names? Regards, Darren Log in or register to post comments
Member for 17 years 2 months Member for 17 years 2 months Submitted by Varun Ram on Tue, 2008-08-26 13:20 Permalink RE: MS Project Duration thanks Darren. I will check these settings. I posted the whole row.
Member for 17 years 9 months Member for 17 years 9 months Submitted by Darren Kosa on Tue, 2008-08-26 12:57 Permalink RE: MS Project Duration Hi Varun, A few of the most likely causes for you to investigate are listed below: 1) Are the default calendar options the same in all the projects? (Tools > Options > Calendar) 2) Are the calendar working times the same? (Tools > Change Working Time) 3) Are the resource Base Calendars the same? (View > Resource Sheet) 4) Are the Task Calendars the same? (In the Gantt View – Insert > Column > Task Calendar) 5) Is the calculation mode set to automatic? (Tools > Options >Calculation) 6) Did you copy the whole row or just the activity names? Regards, Darren
Member for
17 years 2 monthsRE: MS Project Duration
thanks Darren. I will check these settings. I posted the whole row.
Member for
17 years 9 monthsRE: MS Project Duration
Hi Varun,
A few of the most likely causes for you to investigate are listed below:
1) Are the default calendar options the same in all the projects? (Tools > Options > Calendar)
2) Are the calendar working times the same? (Tools > Change Working Time)
3) Are the resource Base Calendars the same? (View > Resource Sheet)
4) Are the Task Calendars the same? (In the Gantt View – Insert > Column > Task Calendar)
5) Is the calculation mode set to automatic? (Tools > Options >Calculation)
6) Did you copy the whole row or just the activity names?
Regards,
Darren