MS Project Duration

Member for

17 years 2 months

thanks Darren. I will check these settings. I posted the whole row.

Member for

17 years 9 months

Hi Varun,



A few of the most likely causes for you to investigate are listed below:



1) Are the default calendar options the same in all the projects? (Tools > Options > Calendar)

2) Are the calendar working times the same? (Tools > Change Working Time)

3) Are the resource Base Calendars the same? (View > Resource Sheet)

4) Are the Task Calendars the same? (In the Gantt View – Insert > Column > Task Calendar)

5) Is the calculation mode set to automatic? (Tools > Options >Calculation)

6) Did you copy the whole row or just the activity names?



Regards,



Darren