Automatic completion

Member for

17 years 9 months

Hi Assaf,



The short answer is no, there isn’t an automated completion function for MS Project.



As a work around you can group by the finish date and then change the relevant % Complete fields to 100%.



The only other course of action is to go down the VBA route, but that’s beyond my capability unfortunately.



Regards,



Darren