Dear Alexandre,

Your advice is really appreciated.

regards

deb

Member for

22 years 9 months

Pranab,

it may be easier to do in P3:

1. Define the WBS structure of your project in P3

2. Make sure you define the upper level to represent the whole project and one level for each outline level in MS Project

3. Apply the WBS to the activities in P3

4. Remove all the Topic activities in P3 (run a filter saying Activty type EQ Topic to display these activities only)

Hope this helps

Alexandre

Member for

18 years 9 months

Hello Aexandre,

How to do that can you please let me know in a step by step manner.

regards

deb

Member for

22 years 9 months

Pranab,

P3 regards MSP summary activities as "Topic activities".

Quote

It is recommended that you remove all Topic Activities by promoting ALL activities to Outline Level 1 and deleting redudant Parent Activities. You will need to check that all logic is at the lowest Outline Level before promoting activities

Unquote

(In "Project Planning Using P3 V3.1" by Paul E. Harris)

Alexandre

Member for

18 years 9 months

Dear Darren,

Thanks a lot, ya by data date i mean status date only.



Now i am having a new problem. i a changing a MSP schedule to a P3 one. in the MSP schedule there are summary activities , these are as well coming to the p3 schedule as activities with huge durations.

Please help.

regards

deb

Member for

17 years 9 months

Hi Deb,



By Data Date I’m assuming you mean Status Date (the last date the project was updated).



Project > Project Information



You can also set the Project Start / Finish Dates and Current Date this way.



To set the project baseline.



Tools > Tracking > Save Baseline



Regards,



Darren